Banco de la República expects Teatro Amira de la Rosa works to finish in the first quarter of 2029
Banco de la República said the intervention at the Teatro Amira de la Rosa in Barranquilla will finish in the first quarter of 2029, not in 2028 as previously expected. The entity said findings of structural damage forced changes to designs and technical procedures to preserve the heritage building and ensure its stability. Foundation and structural reinforcement work is 90% complete, and the first phase of restoring the folded roof has been finished.
In 40 seconds
- Banco de la República expects to deliver the Teatro Amira de la Rosa works in the first quarter of 2029.
- The entity attributes the delay to findings of structural damage that forced changes to designs and technical procedures.
- Foundation and structural reinforcement work is 90% complete and the first phase of the folded roof is finished.
IASummary generated by artificial intelligence from a story by El Espectador. It may contain errors: the original source prevails.




Comments
Be respectful. Comments reported by several people are hidden until a moderator reviews them.
You do not need an account to read, only to comment. Sign in with a code sent to your email or with your Google account. We only show the name you choose, never your email.